Operations Progress Report June 2013

  • Reporting Period Updates:
    • Operations released the first beta of RCE6. RCE6 is based on Enterprise Linux 6 and includes many updated features and new applications.
  • Open issues, questions, or needs
    • None at this time
  • Metrics
    • RT Tickets
      • 25 new tickets escalated to Operations, 24 tickets resolved
      • 28 new project tickets created, 30 project tickets resolved, 182 remaining project tickets
    • RCE Usage
      • RCE login nodes, users: 61
      • Interactive compute nodes, Users: 70 | Processing Hours: 18,915.5
      • Batch compute nodes, Users: 11 |  Processing Hours: 27,346,4

Do you have news to share?

We're always interested in hearing the latest work and accomplishments from IQSS affiliates and would be happy to help you share your news. If you have any updates, let us know!